Tuesday, November 26, 2019

Riveted center ribs on left wing.

Sunday, November 24, 2019

Fabricated right wing false spar and false spar and short rib attach angles.

Friday, November 22, 2019

Fitted short ribs and fabricated left wing false spar.

Wednesday, November 20, 2019

Removed center ribs and nose ribs, deburred and reinstalled.

Monday, November 11, 2019

Sunday, November 10, 2019

Installed center ribs on left wing.

Wednesday, November 6, 2019

Finished right wing nose rib installation. Set left wing rear spar in fixture.

Tuesday, November 5, 2019

Installed half of right wings nose ribs.

Monday, November 4, 2019

Installed right wing center ribs.

Sunday, November 3, 2019

Squared and leveled right wing in jig

Saturday, November 2, 2019

Constructed wing assembly frame.

Friday, November 1, 2019

Welded left wing flap and aileron drive linkage.

Sunday, March 31, 2019

Welded right wing flap and aileron drive linkage.

Thursday, March 7, 2019

Fabricated wing end strut fittings.

Tuesday, March 5, 2019

Finished fuselage wing strut fittings.

Monday, March 4, 2019

Fabrcated aileron cable pulley brackets and started on fuselage wing strut fittings.

Saturday, March 2, 2019

Fabricated aileron hinges and flap support at wing root.

Monday, February 18, 2019

Sunday, February 17, 2019

Saturday, February 16, 2019

Fabricated pieces for aileron bellcranks.

Friday, February 15, 2019

Fabricated aileron and flap drive support frame components.

Wednesday, February 13, 2019

Fabricated aileron and flap drive support brackets.



Saturday, February 9, 2019

Riveted left rear spar rib attach angles.

Friday, February 8, 2019

Removed rib angles and spacers from left rear spar, de-burred prepared for paint and primed.

Wednesday, February 6, 2019

Fitted rib attach angles and spacers to left rear spar.