Fabricated control stick end brackets.
Monday, March 10, 2025
Tuesday, March 4, 2025
Fabricated elevator trim actuator rods and outside horns.
Sunday, March 2, 2025
Saturday, March 1, 2025
Fabricated and installed elevator trim shafts and horns.
Saturday, February 22, 2025
Friday, February 21, 2025
Sunday, February 16, 2025
Fabricated front profiled horizontal stabilizer struts.
Thursday, February 6, 2025
Aligned and drilled horizontal stabilizers to front mount.
Tuesday, February 4, 2025
Fabricated and welded in place horizontal stabilizer front mount.
Monday, February 3, 2025
Fabricated and welded in place horizontal stabilizer rear mount.
Sunday, February 2, 2025
Saturday, February 1, 2025
Fabricated and tacked in place bottom and center rib also the cross brace on tail fin.
Saturday, January 25, 2025
Drilled rudder hinges and installed. Fabricated top tail fin rib.
Friday, January 24, 2025
Wednesday, January 22, 2025
Finished struts by drilling and taping oil fill holes.
Tuesday, January 21, 2025
Sunday, January 19, 2025
Fabricated and welded strut attachment fittings on both legs.
Friday, January 17, 2025
Friday, January 10, 2025
Monday, January 6, 2025
Subscribe to:
Posts (Atom)