Friday, December 29, 2023


 

Welded additional tacks on all vertical fuselage tubes. Removed wooden support structure.

Thursday, December 28, 2023

 Fabricated engine fire wall mount tubes, tacked in place . Installed fire wall cross tubes.

Wednesday, December 27, 2023

 Tacked in place tubes from B to Q.

Tuesday, December 26, 2023


 

Fitted and tacked in place cross tubes below doors.

Sunday, December 24, 2023

 Fitted and tacked in place cross bracing above and below cargo door.



Saturday, December 23, 2023

 Tacked in place cross tubes at stations N,M &L.




Sunday, December 17, 2023

 Fabricated and tacked in place station S.



Friday, December 15, 2023

 Fabricated and tacked into fuselage lower door frames.



Monday, December 11, 2023

 Fabricated and tacked in place remaining cross braces in rear of fuselage.



Friday, December 8, 2023

 Fabricated and installed "V" braces in (H-J) to (F-L).



Thursday, December 7, 2023

 Fabricated fire wall frame, tacked in place with support tubes to station "B".



Wednesday, December 6, 2023

 Fabricated and tacked in place cargo door top and bottom tubes.


 


Tuesday, December 5, 2023

  Fabricated and tacked in place vertical and horizontal fuselage tubes for station B-P.

Monday, December 4, 2023

 Fabricated and tacked in place vertical fuselage tubes for stations E-M and D-N.



Saturday, December 2, 2023

 Fabricated and tacked in place vertical fuselage tubes for station F-L.

Friday, December 1, 2023

 Fabricated and tacked in place vertical fuselage tubes for stations h-j and g-k.